Tuesday, March 29, 2011

Mifgs build day 10

We're finished. Hooray. All done today about 2pm. We are really happy with the result and I'm so proud of the whole team. Everyone has done their part to contribute to this fabulous end result. Beautiful!!

Monday, March 28, 2011

mifgs Build day 9


It's our first late evening and all is going well. We're all down to mulch back drops and finishing touches. Lights by "miles Johnson glass" are all fired up and the moss wall is in place. Com see us at the show. - Wednesday through Sunday.

Mifgs build day 9.


We're on the home stretch. We've added lots of plants and started mulching. Inal coats of paint and small timber finishing. This afternoon we add our vertical and rooftop gardens

Mifgs build day 7&8

Saturday and Sunday has seen a
Lot of great work completed. No photo this time but we've had water delivered put about two thirds of plants in and started all the clear out works. Lighting was installed Saturday and we tested the waterfalls and shower. pressure on tomorrow so we can finish on time tuesday.

Friday, March 25, 2011

Mifgs build day 6


All our greenery arrived today so we're all pretty excited about adding some softness to the landscape. We'll ad water tomorrow an things will really take off!!

Wednesday, March 23, 2011

Mifgs build day 4


Today saw us get some sunshine for once. We've almost finished the floor of the pool. Pit in stairs and stepping stones and even raised the posts for our pool house. The dry stone wall of rubble is coming along amazingly. Tomorrow will see most of our structural work complete. Friday we should get to start planting.

If you can't tell. I'm loving this. Feel free to comment on the photos.

Mifgs build day 3


Today finished great. We're finished the plunge pool walling and the concrete rubble dry stone wave has about 1/3 complete.
Will post again tomorrow

Tuesday, March 22, 2011

Mifgs build day 3.


Today is going really well. Our swimming hole is coming close to the end. Our dry stone walling has begun and the decking is getting in to place.

Monday, March 21, 2011

Garden show build day2


Today we had the full team here. Started building our natural swimming hole and decking. All around us there's a hive of activity as others started their sites too.

Friday, March 18, 2011

The rock is landing


About 2 hours work and we're starting to see our centerpiece rock moving in to place.

Starting at mifgs 2011


Have just started preparation for the build of our display a the Melbourne international flower show.